BMCE Project Update – The raft base of Tower B has been completed on BMCE’s George St project in Croydon The two storey basement excavation is nearly complete and the reinforcement is being fixed for the Tower A base. This landmark structure will be the tallest building in Croydon and the World’s tallest modular structure.

 